A major development has taken place at Jinnah International Airport, as the construction of its main runway using Pavement Quality Concrete (PQC) has been completed earlier than expected, according to the Pakistan Airports Authority (PAA).
This runway, known as 07L/25R, is one of the most important for the airport. It has now been upgraded using modern slip form technology, which is used globally for strong and long-lasting runway surfaces. The PQC phase, which normally takes more than a year in some cases, was impressively completed in just seven months. This marks a big achievement in Pakistan’s push toward modern aviation infrastructure.
Chinese, Pakistani, African Mercenaries Active in Ukraine: President Volodymyr Zelensky
According to the PAA, the airfield lighting system equipment has also been received and installation is now in progress. This advanced lighting system will ensure safe and efficient flight operations, especially during night or poor weather conditions.
In addition to lighting, centerline painting and taxiway marking work is also being done on the upgraded runway. These markings are essential for aircraft navigation and safe taxiing. Once fully completed, this runway will meet international aviation standards, helping Karachi Airport handle increased air traffic safely and efficiently.
This project reflects the growing efforts by Pakistan Airports Authority to bring local airports up to global levels. Jinnah International Airport is one of the busiest in the country, and such upgrades will improve both passenger experience and airline operations.
The early completion of PQC construction on this central runway is not just a technical achievement, but also a sign of Pakistan’s commitment to modernizing its aviation sector.
FAQs
1. What is PQC in runway construction?
PQC stands for Pavement Quality Concrete, a strong and durable material used for building runways.
2. Which runway was upgraded at Karachi Airport?
The main runway 07L/25R at Jinnah International Airport Karachi was upgraded.
3. How long did the construction take?
The PQC construction was completed in just seven months, ahead of schedule.
4. Has the lighting system been installed?
The equipment has been received, and installation is currently underway.
5. What benefits will this runway upgrade bring?
It will improve flight safety, handle more traffic, and meet international standards.